Questions:

Your project team is well underway with the construction of the product of the project. Some of the work has progressed and some deliverables have been reviewed by key stakeholders. During a deliverables review, one of the stakeholders found a discrepancy in one of the deliverables that needed to be addressed immediately. The team reviewed the stakeholder’s issue and agreed that some action needed to be taken to bring the deliverable back into compliance. The best definition for this activity is called:

Select one:

a. Defect repair 
b. Corrective action 
c. Quality control 
d. Preventive action

Answer

Correct Answers: A
Explanation: 

A - Did you think it was a corrective action? Corrective actions are taken to bring the project into line at some future point. Defect repairs address immediate concerns

Register for Online PMP Practice test

To get an access of 1500+ Online Simulated PMP Questions database, you can purchase Full Package of PMP Practice test only in $35 USD. Buy Now 

You also chance to enroll for One Full Length of Free PMP Practice having 200 Questions.
Access will be granted only for 3 days
Sign up for Free PMP Practice test

 

"PMP®","PMI®", "PMI-ACP®" and "PMBOK®" are registered marks of the Project Management Institute, Inc.