Your team is reviewing the project activities and has started to estimate the durations of the work packages identified in the WBS. Some of these work packages and activities have significant uncertainty associated with them for which the team has created contingency buffers. The tool and technique that is used for this process is called:
Select one:

a. Expert judgment 
b. Reserve analysis 
c. Parametric estimating 
d. Three point estimating

Answer

Correct Answers: B
Explanation: 

B – Reserve analysis defines contingency reserves as a method for dealing with schedule uncertainty

Register for Online PMP Practice test

To get an access of 1500+ Online Simulated PMP Questions database, you can purchase Full Package of PMP Practice test only in $35 USD. Buy Now 

You also chance to enroll for One Full Length of Free PMP Practice having 200 Questions.
Access will be granted only for 3 days
Sign up for Free PMP Practice test

 

"PMP®","PMI®", "PMI-ACP®" and "PMBOK®" are registered marks of the Project Management Institute, Inc.